Hi All,
Good day......
First of all, I am sorry for the late reply. My problem is solved during the further investigation I could able to trace out that, the root cause for this solution is work center Scheduling and Capacities formula.
When I changed the formula, my Production dates are calculating correctly.
Thanks for all the replies and efforts.
Regards,
Pushpala.