Planned Delivery Time

$
0
0

Hi SAP experts,

 

I have a client who maintains all their PDT (planned delivery time) within the PIR (Purchasing info record) and not in the material master. They are currently wanting to have the system calculate their safety stock and wanted to know if there was anything that needed to be setup in SAP to trigger SAP to use PIR PDT to calculate safety stock (instead of material master PDT). Or is this a simple case of SAP always uses PIR PDT over material master PDT.

 

Any feedback is appreciated

Regards

Henry