Thank you Amit for your reply.
Data source 2LIS_02_SCN is what we are using for the confirmation of PO schedule line data loading. In the customized program on ECC side, ME_CONFIRMATION_UPDATE_AVIS is being used for the EKES table update, but it does not trigger the delta load of 2LIS_02_SCN when it's executed to update EKES table. That's the problem.
1. Is there a BAPI program can be used for the confirmation of PO schedule like data update?
2. Any solution to resolve this problem that the data via the customized program update can't be loaded to BW through 2LIS_02_SCN delta load?