Hi Szymon,
no we are not using Material Ledger. So far the steps i have done is :
1. create activity types with act acty type cat 1 / act price indicator 7
2. copy planned recovery rates from KP26
3. loaded actual activity rates in KBK6
4. allocated planned activity quantities to PO in KB21N with scr variable 02SAP order
and until here everything is ok.
The problem appears in CON2 where i receive an empty detail list. No senders, receivers or cost element.
thanks!
Regards,
Vasilis